Baucau Hospital Construction At A Standstill

0
135
Diretor Jeral Ministeriu Saude, Jose dos Reis Magno, dezafia no la garantia konstrusaun Ospital Referal Baucau remata iha tinan id a ne’e.

Construction works at the new Baucau Referral Hospital are at a standstill, as the company in charge of the project encountered financial problems with buying construction materials.

General Director Jose dos Reis Magno could not guarantee the construction of the Baucau Referral Hospital would be completed this year.

The General Director at the Ministry of Heath, Jose dos Reis Magno could not guarantee the construction work would finish on December 31, 2013 as stated in the contract between the government and Ensul.

He said the construction work was 56% complete.

In regards to the issue, he said the ministry has called the company to clearly explain their finances, because a large budget was spent on the project.

“After we met and they gave an explanation, we the Administration Council for the Infrastructure Fund decided to extend the contract until April 15, 2014,” said General Director Magno in Kaikoli Dili.

“However, if they don’t finish by the determined date, they will not be given extra government projects for two years, as a sanction.”

“It’s true the works have stopped because of a problem with the budget, not for the government but for the company,” said Magno.

He said based on the criteria they had, the company refused to sign a contract extension but they also could not guarantee the work would be finished this year.

With the declaration of the company, the Ministry of Health gave a letter to the Prime Minister, as the President of the Administrative Council for the Infrastructure Fund, to make a decision. 

The work began in 2010 by the company Ensul with a budget of about $8 million, as it is a big hospital.

Meanwhile, Member of Parliament Eladio Faculto said they shouldn’t extend the contract again and it should be cancelled, as the work has been underway for two years but there hasn’t been significant progress.

According to him, they failed with the works because the company left the site without an engineer, the construction materials were thrown away at random until they rusted and materials expected from overseas hadn’t arrived.

“The government should have a strong method for all companies, not just national companies but also international companies, that don’t comply with their duties,” he said.

Meanwhile the Director of the Baucau Referral Hospital Eugenio Soares said the construction of the new hospital had an impact on treatment in the old hospital, as conditions were unfavourable for patients.

“The impact is also in the treatment, as we cannot extend treatment as there is limited space,” said Soares.

When the TDW journalist tried to confirm issue with Ensul Manager Jose Cordeiros Simoes, he was unavailable for comment.